This thing is taking forever and it is still hot!

Worked on the plumbing on the shop side yesterday. If you see something wrong, let me know cause I ain't no plumber.

Here is a shot of floor drain #1 and the vent/sink drain line on the south wall.
DSCN4118.jpg

Floor drains by code must have a trap primer so here is another vent/sink drain line on the north wall. The two 1/2" pipes are the trap primer lines.
DSCN4117.jpg\ DSCN4119.jpg

I tied the primer lines in on the inlet side of the trap.
DSCN4122.jpg DSCN4128.jpg

I will have two main collection box floor drains that will be 4' long 12" wide and probably about 6" deep. Basically a sink basin cast in the floor with steel bar grating. I'm thinking about adding a 3"-4" wide drain trough between the two floor drains and extend them on the other side of the main drains. They will dump into each basin. I'm thinking about this because I can use those forms down the center so the concrete crew can get the proper slope towards the drain. I'm only going to slope the floor 1" from the outside wall.
DSCN4121.jpg